Timberwolf #2-H Austin Chalk

BOPD = Barrels of oil per day; MCF = Thousand cubic feet of natural gas also the standard unit for gas sales; MCFPD = Thousand cubic feet of natural gas per day . Glossary.

Sorted by Well Name

Timberwolf Drilling Program and Wells

8/11/2008 For the Month of June, the well produced 2955 MCF and 45 Barrels of Oil.

7/17/2008 For the Month of May, the well produced 148 MCF and 12 Barrels of Oil.

6/4/2008 For the month of April, the well produced 90 MCF.

5/12/2008 MPI is only providing monthly totals, so we are unable to post daily averages, as we have previously.

For the month of March, the well produced 80 MCF.

For the month of February, the well produced 4475 MCF and 170 Barrels of Oil.

3/25/2008 MPI reports the well was plugged with mud in January that was cleaned out. The well now has a tubing leak and a workover is being scheduled.

2/24/2008 For the month of January, the well produced a total of 203 Barrels of Oil and averaged 224.97 MCFPD.

1/23/2008 For the month of December, the well averaged 10.24 BOPD and 265.88 MCFPD.

12/26/2007 For the month of November, the well averaged 9.13 BOPD and 236.03 MCFPD.

12/10/2007 For the month of October. the well averaged 10.51 BOPD and 277.58 MCFPD.

11/2/2007 for the month of September, the well averaged 9.16 BOPD and 303.03 MFCPD.

9/25/2007 For the month of August, the well averaged 10.69 BOPD and 309.39 MCFPD.

8/21/2007 For the month of July, the well averaged 12.71 BOPD and 363.35 MCFPD.

7/17/2007 For the month of June, the well averaged 13.08 BOPD and 380.73 MCFPD.

6/28/2007 For the of May, the well averaged 13.41 BOPD and 384.9 MCFPD

5/04/2007 For the month of April, the well averaged 12.66 BOPD and 369.57 MCFPD.

For the month of March, the well was shut in for one day because of a leak, for the 30 days of production the well averaged 15.22 BOPD and 425.20 MCFPD.

4/04/2007  For the month of February, the well was shut in for 4 days for repair, and for the remaining 24 days, the well averaged 17.7 BOPD and 507 MCFPD

2/20/2007  For the month of January, averaged 16 BOPD and 469 Mcfpd for the days it was on line.

1/19/2007 For the month of December, averaged 20 BOPD and 626 MCFPD.

12/12/06 For the month of November, averaged 19 BOPD and 542 MCFPD

11/08/2006 For the month of October, averaged 22 BOPD, and 690 MCFPD

10/10/2006 For the month of September, averaged 24 BOPD and 793 MCFPD

9/06/2006 For the month of August, averaged 27 BOPD and 970 MCFPD

8/22/2006 Flowing 28 BOPD, 1002 MCFPD

7/26/2006 Flowing avg 38 BOPD, 1031 MCFPD (adjusting for pipeline off line for 5 days )

5/10/2006  Flowing 60 BOPD, 1.6 MMCFGPD.

4/13/2006  Flowing 88 BOPD, 2.5 MMCFGPD.

2/14/2006 Flowing 6.3 MMCFGPD and 150 BOPD.

2/6/2006  Production levels during first day of testing -Gas -  9 MMCFPD and 260 BOPD and 450 BWPD, 20/64" choke at 4500 psi flowing tubing pressure.

2/6/2006  Pictures of flare during testing on picture page.  Definitely worth a look.

2/1/2006  Scheduled to start test Thursday 2/2/2006.

1/25/2006 The Unit rig will be moving to the Paul Bunyan No. 1 on Monday the 30th of January. We should begin flowback on February 1st. Fesco will have the well on test for three days with gas being sold and not flared, although the initial 12-15 hours of test production will not be sold due to excessive drilling fluids being produced.  Preliminary estimate of bottom hole pressure is 11,500 psi.

1/19/2006 Reaming liner into south lateral.

1/18/2006 South lateral completed, running liner into lateral and constructing surface facilities.

1/16/2006  Drilling south lateral at 4,000 feet.  Expected to reach TD sometime tomorrow.

1/11/2006  Drilling at around 3,000 feet. 

1/3/2006  Drilling at around 2,000 feet on the south lateral, with 10-30 foot flares using 14.6# mud, numerous signs of fractures.

12/21/2005 North lateral completed, drilling curve for south lateral.

12/12/2005 Drilling at 1200 ft. on north lateral, good shows 20-30 foot flares (see pictures on attached page).

12/8/2005 Finishing drilling curve to kick off point for north lateral.

12/3/2005 Drilled out cement, changed out mud to polymer based mud, going in vertical hole with directional drilling assembly to start drilling curve.

11/28/2005  Ran casing into vertical well bore and are initiating cementing of casing into well bore.

11/23/2005  Drilled to 13,680, cleaning up well bore to prepare to set casing.  Drill pipe currently stuck during that operation.  Circulating oil pills to unstick pipe

11/16/2005 Drilling at 10,455 feet.

11/11/2005 Drilling at 4,465 feet.

11/8/2005  Drilled to 2,060 and cemented in surface casing

11/7/2005 Spudded 11/6/2005; Drilled surface casing hole to 2,030 feet.

 