Frances Evans Sub Clarksville

BOPD = Barrels of oil per day; MCF = Thousand cubic feet of natural gas also the standard unit for gas sales; MCFPD = Thousand cubic feet of natural gas per day . Glossary.

Sorted by Well Name

Brazos Valley 2006-2 Drilling Program and Wells

8/11/2008 For the month of June, the well produced 277 MCF and 125 Barrels of Oil.

7/17/2008 For the Month of May, the well produced 118 MCF and 62 Barrels of Oil.

6/4/2008 For the month of April, the well produced 207 MCF and 83 Barrels of OIl.

5/12/2008 MPI is only providing monthly totals, so we are unable to post daily averages, as we have previously.

For the month of March, the well produced 276 MCF and 124 Barrels of Oil.

For the month of February, the well produced 272 MCF and 104 Barrels of Oil.

2/24/2008 For the month of January, the well produced a total of 129 Barrels of Oil and 20 MCF.

1/23/2008 For the month of December, the well was shut in for most of the month. It produced a total of 55 Barrels of Oil and 267 MCF of gas.

12/26/2007 For the month of November, the well was shut in for most of the month, waiting for a workover. It produced a total of 93 Barrells of Oil and 514 MCF of gas.

12/10/2007 For the month of October, the well was shut in for most of the month, waiting for a workover. It produced a total of 79 Barrels of oil and 129 MCF of gas.

11/2/2007 For the month of September, the well was shut in for most of the month, waiting for a workover. It produced a total of 125 Barrels of oil and 151 MFC of gas.

9/25/2007 For the month of August, the well was shut in for most of the month, waiting for a workover. It produced a total of 123.04 Barrels of Oil and 104 MCF of gas.

8/21/2007 For the month of July, the well was shut in for most of the month, waiting for the workover. It produced 132.21 Barrels of Oil and 573 MCF of gas.

7/17/2007 For the month of June, the well was shut in for most of the month, it appears to be sanded up, which reduces production. A workover is being scheduled to clean up the well. The well produced 146.18 Barrels of Oil and 29 MCF of gas.

3/16/07 Pipeline company running into delays due to some non-cooperative landowners.  New ETA for completion of pipeline is Mid April.

2/13/2007 Pipeline is schedule to be completed in the middle of March.

1/12/2007  Waiting on workover rig to drill out sealer balls of the new Packers Plus Frac System.  Also waiting on installation of pipeline. 

1/04/2007 Well was fracced on 12/22/2006.  It is currently producing about 400,000 cubic feet of gas and 25 barrels of oil, and still unloading over 160 barrels of water.  Pipeline is expected to be connected within the next 3 to 4 weeks.

12/20/2006 Scheduled to be fracced and completed on 12/22/2006.

11/06/2006 Well spudded on 10/25/2006. Currently drilling at 4,086'.

 