Brazos Valley 2006-1 Drilling Program and Wells

8/11/2008 For the month of June, the well produced 1,454 Barrels of Oil.

7/17/2008 For the Month of May, the well produced 1,645 Barrels of Oil.

6/4/2008 For the month of April, the well produced 1,730 Barrels of Oil.

5/12/2008 MPI is only providing monthly totals, so we are unable to post daily averages, as we have previously.

For the month of March, the well produced 1616 Barrels of Oil.

For the month of February, the well produced 1527 Barrels of Oil.

2/24/2008 For the month of January, the well averaged 62 BOPD.

1/23/2008 For the month of December, the well averaged 67.51 BOPD.

12/26/2007 For the month of November, the well averaged 74.7 bOPD.

12/10/2007 For the month of October, the well averaged 65.70 BOPD.

11/2/2007 For the month of September, the well averaged 83.33 BOPD.

9/25/2007 For the month of August, the well averaged 93.82 BOPD.

8/21/2007 For the month of July, the well averaged 106.57 BOPD.

7/17/2007 For the month of June, the well averaged 129.63 BOPD.

6/28/2007 For the month of May, the well averaged 157.98 BOPD.

5/04/2007 For the month of April the well averaged 168.64 BOPD.

 For the month for March, the well averaged 124.43 BOPD.

4/04/07  For the 26 days of the February the well was on line, the well averaged 170.8 BOPD

3/16/07  Averaging 124 BOPD for the month.

3/05/07  Currently averaging 126 BOPD.  Believed to be constricted by sand. Allowing well to work out sand by itself.  If not successful, it will require a workover

2/13/2007 - Production is 240+ BOPD and 133 Barrels per day of frac fluids.

1/30/2007 - Preparing location for production

1/19/2007 The well was fracced yesterday and is now flowing back primarily frac fluids.

1/12/2006  Frac delayed due to malfunction of Packers Plus Frac System.  Malfunction repaired and frac is being rescheduled.

1/04/2007 Drilling completed.  Fracture treatment scheduled between January 10 and January 12.

12/20/2006 Drilling at 2,553' on lateral

12/12/06  Drilling at 1,353’ on lateral

12/07/2006 Curve completed and in process of cementing in the casing.

11/29/2006 Building the curve at 7,776'

11/21/2006 Drilling at 4,269'

11/14/2006 Scheduled to reentering the vertical well on 11/15/2006, and starting process of building curve.

 

 