Watson #1-H Woodbine

BOPD = Barrels of oil per day; MCF = Thousand cubic feet of natural gas also the standard unit for gas sales; MCFPD = Thousand cubic feet of natural gas per day . Glossary.

Sorted by Well Name

2005 Brazos Valley 4 Well Drilling Program and Wells

8/11/2008 For the Month of June, the well produced 1,632 Barrels of Oil.

7/17/2008 For the Month of May, the well produced 1,588 Barrels of Oil.

6/4/2008 For the month of April, the well produced 1,676 Barrels of oil.

5/12/2008 MPI is only providing monthly totals, so we are unable to post daily averages, as we have previously.

For the month of March, the well produced 1,816 Barrels of Oil.

For the month of February, the well produced 1,779 Barrels of Oil.

2/24/2008 For the month of January, the well was online for 26 days and averaged 67.54 BOPD.

1/23/2008 For the month of December, the well averaged 63.19 BOPD.

12/26/2007 For the month of November, th well averaged 68.80 BOPD.

12/10/2007 For the month of October, the well averaged 70.35 BOPD.

11/2/2007 For the month of September, the well averaged 64.93 BOPD.

9/25/2007 For the month of August, the well averaged 77.98 BOPD.

8/21/2007 For the month of July, the well averaged 89.67 BOPD.

7/17/2007 For the month of June, the well averaged 96.59 BOPD.

6/28/2007 For the month of May, the well averaged 117.35 BOPD.

5/04/2007 For the month of April the well was online 11days and averaged 90.25 BOPD.  The well was offline to connect to the pump.

For the month of March the well was online for 8 days and averaged 77.65 BOPD. The well was shut in to clean out sand and put on a pump.

4/04/2007   For the month of February, the well averaged 141.4 BOPD.

2/20/2007  For the month of January, averaged 80 BOPD

1/19/2007  For the month of  December, averaged 61 BOPD

12/12/06 For the month of November, averaged 60 BOPD

11/08/2006 For the month of October, average production was 64 BOPD

10/10/2006 For the month of September, average production was 78 BOPD

9/06/2006 For the month of August, average production was 96 BOPD

7/26/2006 Flowing 94 BOPD

6/27/2006 Flowing 108 BOPD

5/10/2006 Flowing 120 BOPD.  The well will gradually decline in production as the pressure drips until the flow rate is in the 50-75 BOPD range over the next 7-12 months, after which it will be place on a rod pump, and would then be expected to have its production rate rise to the 175-200 BOPD range

4/13/2006 Flowing 160 BOPD

3/20/2006 Flowing 150 Barrels of oil per day.

3/2/2006 Flowing 150-160 Barrels Oil and 45-50 Barrels water at 650psi.  Well is expected to gradually decline over 9-10 months to  75-90 BOPD, at which time it will be placed on rod pump, which should increase the production back to 175-200 BOPD.

2/21/2006 Produced 172 Barrels of oil and 60 barrels of water at 600 pounds flowing tubing pressure

2/14/2006  Fracture treatment in process.

2/6/2006 Drilling finished and liner inserted, waiting on frac treatment.

2/2/2006 Drilling lateral at about 3800 feet.  Expect to TD well tomorrow, install liner over weekend .  Frac scheduled for 2/14 with first production 2/18.  Initial few days of production will be recover of frac fluids.

2/1/2006  Drilling lateral at about 2500 feet

1/25/2006 Completed drilling curve, Set and cemented casing through curve.  Tripping out to let cement set, and will then go in with lateral drilling assembly to begin lateral drill.

1/19/2006  Drilling curve at 8,000 feet.

1/16/2006 Drilling vertical well bore at 6,950 feet.

1/11/2006  Drilled out surface casing.

1/9/2006  Set surface casing.